MONROVIA, Nov 25 (Reuters) - Liberia signed a $5.6 billion infrastructure agreement with Bea Mountain Mining Corporation on Wednesday that would add about 270 megawatts of generating capacity, roughly tripling Liberia's current power output.
The Reuters Power Up newsletter by columnist Ron Bousso provides everything you need to know about the global energy industry. Sign up here.
The deal, called the Master Infrastructure Development Agreement, includes a 100-MW hydropower plant on the Via River, two hydropower plants on the St. Paul River with a combined capacity of 110 MW and a 60-MW biomass plant, the information ministry said in a statement
Three reservoirs built under the project would have a combined storage capacity of 10 billion cubic metres
The centrepiece of the deal is the 146-km (91-mile) Liberia Development Road, which will link the power plants to key economic hubs. A further $1 billion will be invested in other road projects and $230 million in strengthening the national electricity grid
The government said additional revenue generated by higher gold prices at Bea Mountain would help fund the programme, while the company would continue making its regular payments into the Consolidated Account
The project is due to be completed over five years. The biomass plant and transmission lines are scheduled to be finished within two years, boosting Liberia's current generating capacity of 126 MW, according to World Bank data
The agreement will be submitted to the Legislature for consideration, the ministry said
Reporting by Alphonso Toweh. Writing by Ayen Deng Bior. Editing by Mark Potter