The Texas Commission on Environmental Quality (TCEQ) resumed normal air permit reviews for data centers after Gov. Greg Abbott's office told the agency on November 13 that the Electric Reliability Council of Texas (ERCOT) had finished gathering information on data centers' potential community impacts, The Texas Tribune reported. The notice came before ERCOT filed its final reports and 67 days before Democratic Gov.-elect Gina Hinojosa takes office on January 19.
"The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations," TCEQ spokesperson Laura Lopez said in a written statement to The Texas Tribune.
Abbott froze TCEQ permits for data center projects statewide on September 21. "Data centers must pay their own way, protect our grid and water, and complete the ERCOT and TWDB audits. Until they do, TCEQ will issue no permits sought by data center projects," he said at the time.
Stay ahead of AI infrastructure deals. Get Blockspace in your inbox.
Public Citizen said TCEQ approved air permit registrations on November 16 for three data center gas plants totaling about 3,500 MW: SpaceX's Boca Chica plant, the plant serving CloudBurst near San Marcos and Atlas Energy Solutions' plant in Shackelford County. All three used a standard permit registration that required no public notice or comment, and 17 suspended construction approvals were active again by November 13, the group said.
"Texans know how to read a calendar, and they see a lame-duck period when the data center industry is rushing to get in while it can, with the TCEQ apparently willing to go along," said Kathryn Guerra, Public Citizen's TCEQ watchdog campaign director.
What fits before January 19
TCEQ targets 45 days from receipt to final action for standard permits without public notice, 150 days for standard permits with notice and 285 days for new case-by-case New Source Review permits. Those are agency goals, not deadlines. For applications received when reviews resumed, only the 45-day target falls before January 19.
Hinojosa pledged in an October 22 campaign video to impose a ban "on all data center approvals until laws can be passed by the Legislature to protect Texans." The regular session opens January 12. Her pledge does not say how a moratorium would treat pending applications or permits issued before she takes office.
In Hudspeth County, ServerDome Global's proposed $13 billion campus still lacks air permits for its planned power plants, the El Paso Times reported. Co-founder Ryan Wallace told an October 26 community meeting that the company plans behind-the-meter natural gas generation with no interconnection agreement.
On December 10, ERCOT's community impact report, built from 433 survey responses from loads of 25 MW or more, and a separate Batch Zero eligibility report are due to the Public Utility Commission of Texas (PUCT). Neither report covers El Paso or Hudspeth counties, which sit outside ERCOT.
Stay ahead of AI infrastructure deals. Get Blockspace in your inbox.
Enchanted Rock already holds a standard air permit for the proposed power plant at Meta's El Paso campus, but El Paso Electric still needs the PUCT to amend its certificate for the 366 MW McCloud gas plant. A decision is expected in December. Two administrative law judges recommended approval in September only if the utility keeps the plant's costs from being passed on to its other retail customers for the facility's life, and the city of El Paso opposes the application.